February Progress Report

Kevin asked the Director of Works, the geometra Jimmy, to make a report at the end of each month.

Here’s why this report is important:

  1. To make sure the director of works is frequently on site
  2. To ensure he is FORMALLY reporting back on a monthly basis that all works are proceeding as per contract and as per applicable building codes to ensure certification at end of project
  3. To make sure end-of-project certifications are a “formality” and not a point of confusion as the director of works will need only revert to his/her monthlies and other notes
  4. To keep the builder on his toes knowing that every month there will be a document that reviews his prior month’s work

Progress on the project has been steady once they were able to resume work after the bad weather. I’d say we’re 2-3 weeks behind the original schedule, but they say they can make up the time. (See update below the report.)

Here’s the February report.

Geometra;s Work Report for February
Geometra’s Work Report for February
An Update

Today we received the Giorni Persi per Maltempo report. This “Days Lost due to Bad Weather” report says that they have lost 2 days to snow and 5 to rain. (These days would be added to the end of the contract term, if need be.) So we’re a little closer to on schedule than I estimated above.

Back to Work

After 3 weeks of holiday break and over 4 weeks of weather conditions that prevented work at the site, Francisc and his team got back at it. They had some of the rebar columns they had built off-site delivered and they prepared to attach them to the existing rebar.

Here are three photos. Notice the cloudy weather, a dramatic contrast from the beautiful sunny weather in December.

Mud

Finally, the snow at our building site has melted, due to warmer temperatures and some rain. But work on the site has yet to recommence in earnest.

muddy building site in Le MarcheThe problem now is mud. Take a building site, where the basic earthmoving has started, and add snowmelt and rain and you get one big mess.

Apparently, the mud is worse than our contractor, Francisc, expected. He had a big truck come to the site to deliver some steel — it got stuck. From what Kevin says, it was quite the ordeal to get it un-stuck.

Unfortunately, I don’t have (actual) pictures.

Fortunately, Francisc has been able to construct the steel columns off-site. They next step, when practical, is to deliver them to the site, attach them to the foundation steel, and pour the concrete pillars around them.

More good news is that Francisc believes he can make up the time that was lost in January. We’re pleased, but not that surprised. The schedule looked like it had padding built in.

Here’s Kevin’s summary of what the next few weeks should bring:

The overall plan between now and 10 March is for the columns to be erected, the exterior block (anti-seismic poroton block) walls to be constructed for the ground floor, the interior stone wall to be constructed and the exterior stone to be underway. This will all result in a ground floor well into realization. Then, on or about 10 March we can do the critical structural “floor” between ground and 1st floors.

Lastly, our next trip to see the progress and to make some decisions about interior finishes may get delayed from mid-March to early April. That way we’ll be able to see the structure in a more complete form.

Image source: http://www.pixabay.com – No attribution required

Enter Mother Nature

Soon after I published the previous post about project timing, Marche got hit hard, first by a major snowstorm and them by a series of fairly strong earthquakes.

january 2017 snowstorm in le marcheSnow fell over a number of days in mid-January, piling up as high as two meters (6.5 ft) in some villages. (Kevin said there was less in our area, but over 4 feet.)

Then, on January 18, there was a series of four earthquakes in the magnitude range 4.1 – 5.7. These quakes follow the even stronger quakes of last October and August. (There have been more than 45,000 aftershocks since August.)

Rigopiano Hotel before and after avalanche
Hotel Rigopiano – Before and After
Click image to enlarge

The biggest catastrophe was in the region just south of Marche, Abruzzo, also hit hard by snow, where the Hotel Rigopiano was buried by an avalanche set off by the quakes and 29 of the 40 people inside died.

The impact on our project is only on timing. Very little work has been or will be able to be completed in January. Kevin reports that the contractor, Francisc, has been able to do some work in his shop, assembling some of the steel needed for the support columns.

Recent Earthquakes

Click to enlarge, zoom, and move
Pin A: Casa Avventura
Pin B: August Earthquakes
Pin C: October Earthquakes
Pin D: January Earthquakes
Pin E: Rigopiano Hotel

Click to open a larger map

An Update

I showed a list of Marche earthquakes of magnitude over 5.0 in my post about the October quakes.

Here’s an update to that list:

Month/Year Magnitude
Oct 2016 6.6
Aug 2016 6.2
Oct 2016 6.1
Sep 1997 6.1
Oct 1930 5.9
Jan 2017 5.7
Jan 2017 5.6
Oct 2016 5.5
Oct 1943 5.5
Oct 1936 5.5
May 1987 5.1

So the top 3 and 6 of the top 8 have been in the last six months.

Image sources: http://www.telegraph.co.uk/news/2017/01/18/italy-hit-four-powerful-earthquakes-four-hours-bringing-terror/
By TVSEI – https://www.youtube.com/watch?v=6La91fbpbbg, CC BY 3.0, https://commons.wikimedia.org/w/index.php?curid=55271832

Project Timing: Starting 2017

We feel like we’ve made excellent progress on the building project in the last six weeks of 2016.

Kevin sent us a timing plan for the rest of the work, roughly showing activities by month. It stretches the project out until February 2018 — which was the completion date he proposed in October.

Looking at the plan, it feels conservative. There are few concurrent activities, maybe because one contractor and his team are doing much of the work.

Anne can’t understand how it can taKe over a year from where we are now. She really wants to be able to be in the house for Christmas 2017.

I’m a bit more relaxed about the date. I don’t see us being able to furnish and have the house ready until the spring of 2018. That sets us up perfectly for “introducing” the house in the summer 2018. Also, I’d rather take an extra month or two than rush the contractor into cutting corners.

Here’s the project flowchart Kevin sent along.

Workplan for house construction in Le Marche
Workplan Flowchart
Click image to enlarge