April Progress and Lost Days Report Lost Days Up to 18

The report says the project is progressing well and that the work has been completed in accordance with standards. No surprise, as we’ve seen the pictures.

The report does contain a picture, the upper right one, we haven’t seen, of the construction of some interior walls on the ground floor.

Bigger news is that 8 days were lost to bad weather. That brings the cumulative count to 18 days, which would be added to the end of the project, if needed. This is significant only in that it extends the time before which the contractor has to pay daily penalties for lack of completion.

Monthly status report
April Monthly Report
Click image to read report