Today’s email from Kevin was a request for approval to get started on building the access road.
The property sits about a kilometer off Strada Provinciale 129, the road between Colmurano and Urbisaglia. Right now, a rough road that turns into a gravel path as it approaches our property is the connection to the SP129. It’s too steep and rough to get equipment and materials to our site.


So step one in construction is to improve this road. I’m a little unclear how much of this distance needs to be improved, but certainly the last few hundred meters need work. Especially the entrance to our driveway. Right now, it’s a steep, sharp turn. We’re hoping the adjacent farmers will let us reshape it a bit.
Because of the recent earthquakes, there’s a tightening of supply of available contractors, as many are or will be working on earthquake-related projects: inspection, repair, rebuilding.
Kevin said that we could grab a grading contractor if we acted fast. Otherwise, we might face a delay of several weeks. We don’t have a building contract yet, so this would need to be done as a separate deal.
We’ve budgeted 12,000€ for this work. The proposal is for us to sign a contract for the road work and pay 10,000€ this week. Plus 1000€ tax.
Anne and I agreed we should go ahead, so now the project is “on the road.”
Source
Google Earth
Like What You Are Reading?
Join us and receive new posts by email.
Unsubscribe anytime. No spam guarantee. We don't share our list.