Temporary Electrical Supply Line Finally Arrives No Word on Permanent Connection

The last time I wrote about this, about six weeks ago, we were concerned that the lack of electrical supply might just bring the project to a grinding halt.

We had repeatedly been promised “in 30 days” that we’d have the permanent power connection. As that hadn’t happened, Francisc arranged for a temporary contractor connection, which he though he could get in a few days.

Wrong again. It’s taken the last six weeks just to get that.

It’s not much to look at, but it’s critical to keep the project moving.

Temporary Electrical Supply Line
Temporary Electrical Supply Line
Click image to enlarge

I guess we’re still just “30 days” away from having the permanent connection.